September 2009
The Library closed on September 16 to begin interior remodeling work. A temporary location is available to library patrons during construction at 406 West Meeker Street, Suite A.
August 2009
The Library will be closing on September 16 for interior remodeling, which includes adding an automated materials-handling system and reconfiguring the back room. Temporary services will be available.
July 2009
Interior improvements to the Kent Library, including the addition of an automated materials-handling system and reconfiguration of the backroom, has been submitted for permitting. Construction is anticipated to start in late summer 2009.
June 2009
Once permits are received, work to enhance the interior of the Kent Library will get under way. Construction is anticipated to start in the summer of 2009.
May 2009
The addition of an automated materials handling system and reconfiguration of the back room is in process. The final review of design drawings is under way and construction is anticipated to begin in summer 2009.
April 2009
Reconfiguration of the backroom and the addition of an automated materials-handling system is currently under way. The preliminary designs for the public restrooms are completed and interior remodel work is anticipated to start in the summer of 2009.
March 2009
The preliminary designs for some of the interior remodel work have been completed and construction is anticipated to start in Summer 2009.
February 2009
Planning is underway for the addition of an automated materials-handling system and reconfiguration of the backroom. Construction is anticipated to start in Summer 2009.