Sammamish Library Construction Project

The Details:
The design process for the new 19,500 square foot Sammamish Library is underway.
The $8.2 million library will be located in a new development adjacent to Sammamish
City Hall, called Sammamish Commons. The new library will include more books,
materials, computers, space for children and teens and a community meeting room.
Potential Modifications:
A possible adjustment to the project may include altering the budget due to an exceedingly high service demand and limited access to other libraries. This also is an area that is projected to have one of the highest growth rates during the next several decades.
Before any alterations are made, they must be formally approved by the Board.
- Project Status: In progress
- Proposed Start of Construction: Fall 2008
- Estimated Date of Completion: 2010
- New Library Address: 228th Avenue and Southeast Eighth Street
- Architect: Perkins + Will
Highlights:
Design Concepts and Sustainable Strategies from the January 15, 2008 Public Meeting.
View the Slide Show that was presented by architects with Perkins +
Will at a public meeting on November 7, 2007. The plans are preliminary and have
not yet been finalized.
Find out how this library design adheres to green
standards.
See answers to some Frequently Asked Questions
Most Recent Update:
April 2008
Design work is progressing on the library and parking project at Sammamish
Commons. The consultant team is preparing the construction documents needed for
the building permit application and a site development permit is currently being
reviewed by the City. The current timeline includes issuing a bid for contractors
in July 2008. It is hoped that the permit review comments and the final steps
in the city review process will be completed by July 2008.